Sashabaw Road Reconstruction (Maybee to Waldon) Sashabaw Road Reconstruction (Maybee to Waldon)
ROADWAY DESIGN // Sashabaw Road Reconstruction

Reconstruction of 1.9 km of Sashabaw Road from two lanes to a 4-lane boulevard.  The project includes approximately 2 km of new 400 mm watermain, and coordinating storm design with the Township's regional detention design.  (Regional system also designed by HRC.)  In compliance with the Township's Master Safety Path plan, safety paths were constructed the entire length of the project.  Coordinated the design with private utility relocation that included major new facilities for growing regional area.

HRC responsibilities included:

  • Topographic Survey
  • MDEQ Permit Application
  • Cost Estimate
  • Watermain Design
  • Traffic Signals
  • Construction Plans and Specifications
  • Construction Traffic Control
  • Construction Staging Plans
  • Maintaining Traffic Plans
  • Permanent Signing
  • Pavement Markings
  • Preparation of Legal Documents
  • Right-of-Way Acquisition
  • Utility Coordination

The project was funded through MDOT and FHWA.

Construction Engineering and Testing
Adjacent areas were being developed during design and construction phases requiring additional coordination of construction staging and also utility installation.

Right-of-Way/Easement Acquisition
HRC actively obtained the complete property acquisitions for this project.  HRC staff coordinated the title search activities with the ordering of the required Real Estate appraisals.  HRC's Survey Department prepared all of the documents that were required, including the legal descriptions of the takings, drawings and using the RCOC Real Estate actual conveyance documents.  The total number of parcels reflects all fee purchases, and easements.


Client
Road Commission for Oakland County