Q: |
Will I have access to my driveway/parking area? |
A: |
Yes. Contractor intends to maintain two-way traffic along Liberty Drive for as much of the project as practically possible. However, there will be times when due to excavation and paving activities, traffic may be limited to only one lane for short periods of time. Further, there may be some isolated instances when due to concrete curing, access to driveways may be temporarily unavailable. These inconveniences will be kept to a minimum and businesses will be notified in advance of these occurrences. Also, please keep in mind that there are 2 access points to the industrial park. So there may be times where it may be more efficient to use the second entrance to the sub if the contractors work is impeding access to the first one. |
Q: |
Will my mail service be interrupted? |
A: |
No. The Contractor is responsible to provide access to the mailboxes during construction. This may include temporary relocation of the mailboxes depending on construction activities around their immediate vicinity. |
Q: |
Will emergency access be available at all times? |
A: |
Yes. |
Q: |
My sprinklers were damaged during construction. Will they be fixed? |
A: |
Yes. If the Contractor causes damage to your sprinklers during construction, they will be repaired by the Contractor prior to lawn restoration. To help the Contractor in this matter and minimize damages, we recommend that each business mark the location of their sprinkler line and heads along the frontage of their property. |
Q: |
Who do I contact if I have a question? |
A: |
If your question relates to a field matter, please contact the HRC on-site observer. This contact information is provided as a tab on the right side of this page. If your question is more of a policy or non-field matter, contact Deanna Murphy at the City DPW or Joe Heintz at HRC. |
Q: |
How often will this web site be updated? |
A: |
HRC intends to update information on this web site at certain milestones in the progress schedule (initial start-up, completion of aggregate placement, placement of asphalt, completion of construction, etc.). HRC will also be updating the site approximately every two weeks during times of regular construction operations. During periods of inactivity, the updates will be less frequent. |
Q: |
How long will the project take to complete? |
A: |
A preliminary project schedule is included in a link on the right side of this page. This preliminary project schedule was developed at the beginning on this project and is subject to change depending on field conditions and weather. As part of the regular updates, HRC will provide information as to how the construction activities are following this preliminary project schedule. |