The contractor is completing the sidewalk ramps for the road crossings and the sidewalk near the Potter/Beck Road intersection. The entire main line sidewalk has been installed except for a small section near the ITC overhead electrical transmission line property. Lawn restoration will begin in the next few weeks. |
|
|
August 23 thru September 12, 2010
The contractor is completing the sidewalk ramps for the road crossings and the sidewalk near the Potter/Beck Road intersection. The entire main line sidewalk has been installed except for a small section near the ITC overhead electrical transmission line property. Lawn restoration will begin in the next few weeks. |
|
|
August 2 thru August 22, 2010
The contractor will be installing the safety path from Wixom Road to Beechnut and starting the removals of the sidewalk ramps near Andover. The grading and restoration of the lawns is anticipated to begin in mid September. |
|
|
July 26 thru August 1, 2010
The construction of the safety path will begin this week with tree removals. The contractor will begin grading for the safety path starting along Wixom Road and working to the East. Access to driveways may be temporarily prohibited while the contractor removes pavement and install the path through the drives. Access will be restored as soon as possible and some properties will need temporary gravel approaches for a few days while the concrete cures. |
|
|
June 9, 2010 Update
The public info meeting for residents was held today. The scope of work, preliminary schedule, method of maintaining traffic, and the important of construction site safety were discussed. Project flyers containing responsible party contact information were handed out to all attendees. These handouts are available on this website. A copy of the construction plans was also available for residents to view and address any specific issues. |
| |