ABOUT HRC SERVICES PRESS ROOM CAREERS Bid Information - Advertisement, Plan Holder List, Bid Tabulation CONTACT US

Project Updates

Select a hyperlink below to display a brief status report of the project.

May 17, 2010 Update
May 14, 2010 Update
May 11, 2010 Update
May 6, 2010 Update

May 17, 2010 Update

HRC staff completed the manhole inspections on Friday, May 14th.  All SSES field work is complete. 

May 14, 2010 Update

Manhole inspections were cancelled from the Wednesday, May 12th, due to weather conditions.  Postponement date is preliminarily scheduled for Friday, May 14th. 

May 11, 2010 Update

HRC staff completed the smoke testing of the sanitary sewers on Monday, May 10th.  Manhole inspections are planned to occur on Wednesday, May 12th, weather permitting.  The inspections are expected to be concluded that day, subject to weather conditions. 

 
May 6, 2010 Update

HRC staff is planning to commence with the smoke testing of the sanitary sewers on Monday, May 10th, weather permitting.  They expect the work to be concluded during that week, subject to weather and how many issues are discovered in the field. 

 


<- Back to Top




HOME CONTACT US LOCATIONS SEARCH