June 27 thru July 3, 2011
The water main along North Road will be shut down between 8 AM and 12 PM to make the connection between the existing water system and the new water main. Water service along North Road from Adelaide to Oak Park will be unavailable during this time. The contractor will continue throughout the week to make connections from the existing side street water mains to the new water main and to transfer over individual water services. Water service to individual properties will be unavailable for a few hours while the contractor is transferring over the individual water services.
|
November 15 thru November 29, 2010
Installation of the final course of new pavement is scheduled for November 16 & 17. Temporary road closures will occur during the paving operations. During the week of November 21 thru 27 the roadway will be striped, sprinkler lines repaired and general clean up of the site prior to shut down for the winter. The seeding for the lawn restoration will not occur until Spring 2011 when better growing conditions are present. |
|
|
November 2 thru November 14, 2010
Once all of the concrete sidewalks have been poured the road paving and remaining driveways will be installed along Adelaide from S. Holly Road to Silver Lake Road. Road paving is tentatively scheduled for the week of November 8 thru 13, 2010. Temporary road closures will occur during the paving operations. |
|
|
October 14, 2010
thru November 1, 2010
The water main installation is complete with only a few connections to be made. Concrete curb and gutter repairs and sidewalk replacements will begin the week of October 18th. During the remaining time the roadway will be graded and prepped for pavement installation. |
|
|
August 1, 2010
thru October 13, 2010
The contractor will be installing the water main and water services between South Holly Road and Silver Lake Road.
|
|
|
July 26, 2010
thru August, 2010
The contractor will be installing the traffic control signs and soil erosion control measures for the first phase of the project from South Holly Road to Silver Lake Road. The route will be prepped for installation of the new water main.
|
|
|
April thru July 26, 2010
The project is currently being reviewed by contractors for submittal of bids. Once a contractor has been selected and a project schedule is available this section will be updated.
|
|
|